KDP BUILDWELL PVT. LTD. V. DEEPAK KUMAR TOMAR

1. KDP BUILDWELL PVT. LTD.
SECTOR 6
NOIDA

Versus

1. DEEPAK KUMAR TOMAR
99A, VISHNU ENCLAVE DELHI HAPUR ROAD
GHAIABDAD
UP

Case No: FIRST APPEAL NO. 242 OF 2020

Date of Judgement: 06 Jan 2023

Judges:

For the Appellant : Ms. Astha Tyagi, Advocate with Ms. Diksha Narula, Advocate
For the Respondent : Mr. Yash Tandon, Advocate

Facts:

The matter relates to a builder-buyer dispute regarding a residential unit. Builder KDP Buildwell Pvt. Ltd. and buyer Deepak Kumar Tomar entered into an agreement on 28.08.2013. The assured date for delivery of possession was 36 months from 28.08.2013, which elapsed on 27.08.2016. Possession was not delivered within the assured period or within a reasonable period thereafter. Buyer filed a consumer complaint before the State Commission Uttar Pradesh claiming refund with interest. State Commission ordered the builder to refund the amount of Rs. 20,33,805/- deposited by the buyer along with interest at 18% p.a. from respective dates of deposits till realisation. It also awarded Rs. 10,000/- as cost of litigation. Builder has filed the present First Appeal challenging only the rate of interest and cost awarded, not the primary liability to refund amounts deposited.

Arguments by Builder:

Builder admitted the delay and liability to refund deposited amounts. It confined the First Appeal only to issues of rate of interest and cost awarded. Builder submitted it was ready to refund the principal deposit amount as per order dated 18.02.2020, but failed to comply. Builder argued that interest rate of 18% p.a. awarded by State Commission is very high. It submitted that rate of interest of 9% p.a. would be fair and reasonable.

Arguments by Buyer:

Buyer argued he has suffered continuous harassment due to delay by the builder. Although State Commission awarded 18% interest, buyer submitted he would be satisfied if compensatory interest is provided at 12% p.a. Buyer submitted that any rate lesser than 12% would not be fair or reasonable.

Court’s Opinion:

The Presiding Member analyzed the principles for grant of compensation under Section 14 of the Consumer Protection Act, 1986. He observed that the law does not provide any standard methodology to quantify exact loss/injury suffered by a consumer. Compensation has to be assessed based on facts and circumstances of each case. Builder failed to deliver possession within agreed timeline or even a reasonable period thereafter. Builder also failed to comply with order dated 18.02.2020 where it undertook to refund deposited amounts within 8 weeks. Court held that buyer has suffered loss which deserves reasonable compensation. Court was of the view that interest rate of 12% p.a. would be just and equitable in facts and circumstances of the case.

Relevant Sections:

Cases Referred:

No specific case laws have been cited or referred.

Final Decision:

Download Court Copy: https://dreamlaw.in/wp-content/uploads/2024/02/42.pdf

Full Text of Judgment:

2. Heard the learned counsel for the appellant (the ‘builder co.’) and the learned counsel for the respondent (the ‘complainant’). Also perused the record including inter alia the State Commission’s impugned Order dated 08.01.2019 and the memorandum of appeal.
3. The matter relates to a builder-buyer dispute. Briefly, the builder co. entered into an agreement with the complainant on 28.08.2013 in respect of a residential unit. The assured date for delivery of possession of the subject unit was 36 months from the date of execution of the agreement. The same elapsed on 27.08.2016. Delivery of possession was not made within the assured period, nor was it even made within a reasonable period thence (reasonable period here would connote a period which may appear reasonable per se and which a reasonable man of ordinary prudence would not normally agitate or object to). The State Commission ordered the builder co. to refund the deposited amount with compensation in the form of simple interest at the rate of 18% per annum from the respective dates of deposit till actual realisation. It also awarded Rs. 10,000/- as cost of litigation.
4. The builder co. preferred the present appeal before this Commission. On 18.02.2020, at the stage of admission, this Commission passed the following Order:
1. Heard learned counsel for the appellant. Perused the material on record.
2. The award made by the State Commission vide its impugned Order dated 08.01.2019 reads as below:

ORDER

The complaint is partially accepted and opposition is ordered that, he should return the complainant’s deposit amount of Rs.20,33,805/- to the complainant at the rate of 18 percent per annum from the date of deposit to the date of payment. Rs.10,000/- should also be paid to the opposition to complainant for case expenses.

3. It is admitted that [a] the agreed and assured date of completion has elapsed and [b] the completion- cumoccupancy certificate of the subject unit has as yet not been duly obtained.

4. During the course of the arguments, learned counsel for the appellant submits, on instructions, that the appellant is ready and willing to refund the principal amount of Rs. 20,33,805/- to the respondent complainant within 8 weeks from today. Learned counsel further submits that the instant first appeal may hereinafter be confined and restricted to the questions of rate of interest and cost of litigation only.
5. The above submissions, made on instructions, during arguments, are recorded.
6. The appellant is directed to refund the entire principal amount of Rs. 20,33,805/- to the respondent complainant within 8 weeks from today, as submitted and assured.
7. This instant first appeal shall hereinafter be confined and restricted to the questions of rate of interest and cost of litigation only.
8. Issue notice to the respondent complainant, subject to payment of Rs. 20,000/- to the respondent complainant within 6 weeks from today to defray travel and allied expenses.
9. The Registry may ensure that the notice is issued and despatched within 10 days.
10. Let the notice also be ‘dasti’ in addition.
11. The appellant is directed to ensure the due ‘dasti’ service of the notice on the respondent, without fail, before the next date of hearing.
12. Contingent to the entire principal amount of Rs. 20,33,805/- being paid to the complainant within the submitted and assured period of 8 weeks from today, the operation of the impugned Order dated 08.01.2019 of the State Commission insofar as it relates to payment of interest and cost of litigation shall remain stayed till the disposal of this first appeal.
13. It is made clear that if the entire principal amount of Rs. 20,33,805/- is not paid to the complainant within the submitted and assured period of 8 weeks from today, the State Commission shall undertake execution of its Order in its entirety as per the law.
14. List on 09.09.2020.
15. ‘Dasti’, in addition, to facilitate timely compliance.
5. Learned counsel for the builder co. submits that the above-quoted Order dated 18.02.2020 has not been put to review or challenge. In reference to para 4 thereof, learned counsel submits that the amount of Rs. 20,33,805/- deposited by the complainant has not been refunded to him. Learned counsel re-confirms that the builder co. is confining and restricting its present appeal to the questions of rate of interest and cost of litigation only.
6. In so far as the cost of litigation is concerned, on the face of it itself the amount of Rs. 10,000/- awarded by the State Commission appears to be entirely reasonable and most obviously does not call for any dilution.
7. Regarding the rate of interest, the State Commission has awarded the compensation by way of simple interest at the rate of 18% per annum on the deposited amount from the respective dates of deposit till actual realisation. Learned counsel for the builder co. submits that the rate of interest of 18% per annum is unreasonably high. In her opinion a rate of 9% per annum will be fair and reasonable. Submission is that the builder co. is willing and ready to pay compensatory interest only at the rate of 9% per annum. Learned counsel for the complainant, on the other hand, submits that the complainant has been put to continuous troubles and travails. He but further submits that in order to put a period to the lis, rather than interest at the rate of 18% per annum as awarded by the State Commission, the complainant will be satisfied if he is provided the compensatory interest at the rate of 12% per annum. Submission is that rate less than 12% per annum will not be in any eventuality either fair or reasonable.
9. While reverting to the facts of the case at hand, it is noted that the complainant had deposited total Rs.20,33,805/- with the builder co. between August and October 2013. The assured period of delivery of possession of the subject unit elapsed in August 2016. The builder co. did not deliver possession of the subject unit within the assured period, or even within a reasonable period thence. At the time of admission of the present appeal a submission was made on 18.02.2020 on its behalf that it will refund the deposited amount within eight weeks, but the assurance proved to be just a ruse and was not fulfilled. Pertinently in its present
appeal the deficiency per se committed by it is not being contested and its challenge is being limited to the rate of the compensatory interest and the cost of litigation only. The afore contextual backdrop encapsulates the jeopardy to which the complainant has been put to, the uncertainty and difficulty he has faced, the mental agony and physical harassment he has suffered, the pecuniary loss to which he has been subjected to, and the cumulative injury which he has endured as a result of all this.
11. Sequel to the above, the award made by the State Commission is modified to the extent that the builder co. through its managing director shall forthwith refund an amount of Rs. Rs.20,33,805/- to the complainant with interest at the rate of 12% per annum from the respective dates of deposit till actual realisation along with cost of litigation of Rs. 10,000/-, failing which the State Commission shall undertake execution, for ‘enforcement’ and for ‘penalty’, as per the law.
12. The Registry is requested to send a copy each of this Order to the parties in the appeal and to their learned counsel as well as to the State Commission immediately. The stenographer is requested to upload this Order on the website of this Commission immediately.